Question 1

Scrum practices are facilitated by the:

  • A. ScrumMaster.
  • B. Product Owner.
  • C. Project Sponsor.
  • D. Scrum team.
Answer:

A

Discussions

Question 2

DRAG DROP
Sequence the steps to User Story Mapping.
Select and Place:

Answer:

Explanation:
1. Product Roadmap Definition
2. User Story Definition
3. User Story Decomposition
4. Release Planning

Discussions

Question 3

What key benefits might stakeholders realize from an Agile approach?

  • A. The ability to bypass the change-management process, inserting new requirements and changes directly into the team as they meet daily
  • B. The early and continuous delivery of valuable software, providing increased visibility and the opportunity for more frequent adjustments
  • C. Increased access to the project and less reliance on formal reports and status meetings to better understand the current work and the risks the team is accepting
  • D. The teams flexibility to make changes mid-iteration as business needs or priorities change, increasing the ability of the team to meet project commitments
Answer:

B

Discussions

Question 4

After seeing the planned features for an upcoming release, a customer notes that a vitally important and complex one is
missing. The team estimates that this feature significantly exceeds its average velocity.
How can this issue be resolved?

  • A. Break down the feature into smaller parts, and commit to completing the minimum viable product.
  • B. Complete the iteration to which they have already committed, and include the feature in the next release.
  • C. Change the planned features to include only the vitally important one.
  • D. Extend the iteration to complete the feature.
Answer:

D

Discussions

Question 5

An agile team member identifies a potential problem within the project team.
How should the teams coach react?

  • A. Document the problem, escalate to the project manager, and develop a solution for the team
  • B. Add the problem to the backlog and assign resolution to a future iteration
  • C. Instruct the team to try to solve the problem within the team
  • D. Perform root cause analysis and report the problem to the product owner
Answer:

A

Discussions

Question 6

The Project Manager plays the following role in Scrum:

  • A. Collects the status from the Scrum Master
  • B. Updates the Burndown chart
  • C. Creates the release plan
  • D. There is no project manager role in Scrum
Answer:

D

Discussions

Question 7

What is the best description of the relationship between Scrum and extremeProgramming(XP)?

  • A. XP is a component of Scrum.
  • B. The principles of each are often complementary.
  • C. Scrum is a component of XP.
  • D. The principles of each are often contradictory.
Answer:

B

Discussions

Question 8

Continuous attention to_____________ and good design enhances agility.

  • A. Best architectures
  • B. Technical excellence
  • C. Robust plans
  • D. Change control
Answer:

B

Discussions

Question 9

What is the Agile Open Space concept?

  • A. When cubicles walls are removed for an Agile team.
  • B. It is a meeting designed to allow Agile practitioners to meet in self-organizing groups where they can share their latest ideas and challenges.
  • C. The choice to collocate all team members for the beginning of a project.
  • D. It is a core principle of ADSM
Answer:

B

Discussions

Question 10

The measure of productivity of a Kanban team is:

  • A. Cycle time
  • B. Lead Time
  • C. Work in Progress
  • D. Velocity
  • E. Throughput
Answer:

E

Discussions