A project manager has developed the initial schedule for an upcoming project.
Using the attached schedule, which of the following is the critical path?
A
A milestone task on the critical path has been completed.
Which of the following should the project manager notify?
C
A new project manager is working in an environment where resources report to another supervisor. The project manager is
having difficulty with a particular member and wants to escalate the issue. Which of the following documents should the
project manager consult?
B
While working with a project team to create the project schedule, which of the following must occur for performance
measurement?
D
Explanation:
The project management plan contains the project management baseline data (typically cost, schedule, and scope), which
youll use to monitor and compare performance measurements against.
A stakeholder is unaware of a projects status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project
changes? (Choose two.)
A D
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the
expected outcomes.
Which of the following best describes what the PM should work on FIRST?
B
A software development project is struggling with a certain technology that is unknown to the project team. A project
manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do
NEXT?
E
A customer-requested project change has been approved, implemented, and validated.
Which of the following should the project manager do NEXT?
D
Midway through a project, the building the team works in is destroyed by a hurricane. Which of the following types of
communication is BEST in this event?
B
A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign
resources. Which of the following should the project manager use to answer the question?
B