comptia jk0-017 online test

CompTIA E2C Project+ Certification Exam

What students need to know about the jk0-017 exam

  • Total 402 Questions & Answers

Question 1 Topic 1

Topic 1
A project manager has failed to obtain the necessary permits from the local building commission. The project has been
stopped because of a failure to understand the importance of:

  • A. internal process compliance.
  • B. risk avoidance.
  • C. standards compliance.
  • D. audit trail compliance.
Answer:

C

Discussions

Question 2 Topic 1

Topic 1
In which of the following organization types would a project manager have the MOST
authority?

  • A. Projectized
  • B. Balanced Matrix
  • C. Weak Matrix
  • D. Functional
Answer:

A

Discussions

Question 3 Topic 1

Topic 1
Which of the following steps should a project manager take to ensure the quality of project deliverables for a customer?
(Select Two).

  • A. The project manager should consult the project sponsor and customer to review the current quality requirements.
  • B. The project manager should request a peer review of the project to determine if it meets the customers quality standards.
  • C. The project manager should change the scope of the project to meet the customers expectations of quality standards.
  • D. The project manager should check the finished product to determine if it meets the customers quality standards.
  • E. The project manager should outsource to obtain the best resources for the project.
Answer:

B D

Discussions

Question 4 Topic 1

Topic 1
A project manager has a project with staff in four different countries. When generating the resource management plan, which
of the following should be considered FIRST?

  • A. Reviewing holiday and vacation schedule with all team members.
  • B. Getting the email address of all the employees.
  • C. Locating each employee on the map in the office.
  • D. Understanding the international country code of all the team members.
Answer:

A

Discussions

Question 5 Topic 1

Topic 1
Which of the following occurs during a project kick-off meeting? (Select Two).

  • A. Work performance information is established.
  • B. Risk analysis is performed.
  • C. Quality metrics are defined.
  • D. Project goals are communicated.
  • E. Roles and responsibilities of the project team are identified.
Answer:

D E

Discussions

Question 6 Topic 1

Topic 1
Which of the following should be created in the project closing documentation? (Select
Two).

  • A. Closure report summarizing costs
  • B. Responsibility assessment matrix
  • C. Lessons learned
  • D. Project timeline
  • E. Statement of Work (SOW)
Answer:

A C

Discussions

Question 7 Topic 1

Topic 1
Which of the following methods would a project manager use to estimate the construction cost of a 2,000 square foot home
when given the cost per square foot?

  • A. Parametric estimating
  • B. Analogous estimating
  • C. Top-down estimating
  • D. Bottom-up estimating
Answer:

A

Discussions

Question 8 Topic 1

Topic 1
After final acceptance, which of the following would the project manager use to assess the strengths and weaknesses of the
project?

  • A. Post-project review
  • B. Transition plan
  • C. Project kick-off meeting
  • D. Quality analysis
Answer:

A

Discussions

Question 9 Topic 1

Topic 1
A cause and effect diagram can also be called:

  • A. a control chart.
  • B. a scatter diagram.
  • C. an Ishikawa diagram.
  • D. a Pareto Chart.
Answer:

C

Discussions

Question 10 Topic 1

Topic 1
A project manager is performing activity sequencing using the arrow diagramming method
(ADM). Which of the following is true of ADM?

  • A. ADM can only represent finish to start dependencies.
  • B. ADM cannot represent multiple successor activities.
  • C. ADM can only represent activities that are on the critical path.
  • D. ADM uses boxes representing activities, and arrows to represent dependencies.
Answer:

A

Discussions