Topic 1
A project manager has failed to obtain the necessary permits from the local building commission. The project has been
stopped because of a failure to understand the importance of:
C
Topic 1
In which of the following organization types would a project manager have the MOST
authority?
A
Topic 1
Which of the following steps should a project manager take to ensure the quality of project deliverables for a customer?
(Select Two).
B D
Topic 1
A project manager has a project with staff in four different countries. When generating the resource management plan, which
of the following should be considered FIRST?
A
Topic 1
Which of the following occurs during a project kick-off meeting? (Select Two).
D E
Topic 1
Which of the following should be created in the project closing documentation? (Select
Two).
A C
Topic 1
Which of the following methods would a project manager use to estimate the construction cost of a 2,000 square foot home
when given the cost per square foot?
A
Topic 1
After final acceptance, which of the following would the project manager use to assess the strengths and weaknesses of the
project?
A
Topic 1
A cause and effect diagram can also be called:
C
Topic 1
A project manager is performing activity sequencing using the arrow diagramming method
(ADM). Which of the following is true of ADM?
A