Whose interests are specifically represented by the senior supplier?
1. Those ensuring the project is value for money.
2. Those who will use the projects products.
3. Those who will be developing the projects products.
4. Those responsible for the projects technical integrity.

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Answer:

C

Reference:
https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_206&showNav=true&exp
andNav=true

Discussions

Question 2

Which is a key objective of running a workshop?

  • A. To make daily progress visible to the delivery team and key stakeholders
  • B. To encourage collaboration and create the defined outputs from the event
  • C. To communicate decisions to the wider stakeholder community
  • D. To make day-to-day decisions on behalf of the delivery team within a sprint
Answer:

B

Reference:
https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_166&showNav=true&ex
pandNav=true

Discussions

Question 3

Which statement about the waterfall methodology definition is CORRECT?

  • A. It states that deadlines should not be moved
  • B. It has distinct goals for each stage of development
  • C. It is a behavior that involves making things transparent
  • D. It promotes the use of experiments carried out in a scientific way
Answer:

B

Reference:
https://www.lucidchart.com/blog/agile-vs-waterfall-vs-kanban-vs-scrum

Discussions

Question 4

How should product-based planning be used as part of PRINCE2 Agile?

  • A. To track progress against the team plan
  • B. To create the project plan using empiricism
  • C. To enable team planning to be predictive
  • D. To plan by focusing on the features required
Answer:

D

Reference:
https://worldofagile.com/blog/product-based-planning-technique-in-prince2/

Discussions

Question 5

Which statement about the ‘directing a project’ process is CORRECT?

  • A. The project board should attend regular project progress meetings
  • B. The project board should make decisions based on the Agilometer risks
  • C. A project board member should fulfill the product owner role within a delivery team
  • D. The project board should increase the stage-level time tolerance
Answer:

C

Reference:
https://www.prince2primer.com/directing-a-project-3/

Discussions

Question 6

Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Answer:

C

Reference:
https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_190&showNav=true&exp
andNav=true#:~:text=A%20highlight%20report%20is%20used,at%20intervals%20defined
%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20co
uld%20help

Discussions

Question 7

To help with prioritization, what is MOST important when understanding the difference between
scope and quality?

  • A. Combining functional and non-functional requirements
  • B. Creating non-functional requirements with user stories
  • C. Differentiating functional from non-functional requirements
  • D. Defining non-functional requirements before functional requirements
Answer:

C

Discussions

Question 8

Why is Lean Startup included in the ‘starting up a project’ process in PRINCE2 Agile?

  • A. Because it explains how a small company can grow using traditional technologies
  • B. Because it is designed to manage projects, delivering products in timeboxes
  • C. Because it enables agile to be used in challenging and uncertain situations
  • D. Because running a project and setting up a new business are the same
Answer:

C

Reference:
https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_127&showNav=true&ex
pandNav=true

Discussions

Question 9

Which process can take place during a release review workshop?

  • A. Controlling a stage
  • B. Managing product delivery
  • C. Managing a stage boundary
  • D. Directing a project
Answer:

B

Discussions

Question 10

Which BEST describes the senior user role when tailoring the organization theme?

  • A. An ‘agile sponsor’
  • B. An ‘executive sponsor’
  • C. A ‘coach’
  • D. A ‘super product owner’
Answer:

D