Huawei h12-425 online test

HCIP-Data Center Facility Deployment V1.0 Exam

What students need to know about the h12-425 exam

  • Total 240 Questions & Answers

Question 1

Site selection is one challenge for the traditional data center

  • A. TRUE
  • B. FALSE
Answer:

A

Discussions

Question 2

Unpredictable business, expansion and difficult investment is one of the challenges facing the
development of traditional data center business.

  • A. TRUE
  • B. FALSE
Answer:

A

Discussions

Question 3

Which system affects the PUE most in Data Center.

  • A. Power Distribution system
  • B. Cooling System
  • C. N/A
  • D. Lighting system
Answer:

B

Discussions

Question 4

Which one is the best PUE in the following:
A. 1.06
B. 2
C. 0.3
D. -0.5

Answer:

A
//en.wikipedia.org/wiki/Power_usage_effectiveness

Discussions

Question 5

Cold/Hot aisle containment is used to solve the problem of heat dissipation in Data Center.

  • A. TRUE
  • B. FALSE
Answer:

A

Discussions

Question 6

Modular Data Center is on-demand deployment, which avoids over-investment.

  • A. TRUE
  • B. FALSE
Answer:

A

Discussions

Question 7

Which Technologies or solutions can reduce PUE?

  • A. Increasing the number of access control systems
  • B. Efficient modular UPS
  • C. Cold/hot aisle containment
  • D. In-row cooling
Answer:

BCD

Discussions

Question 8

FusionModule2000 is an outdoor smart modular data center solution.
A. TRUE
B. FALSE

Answer:

B
FusionModule2000 is an indoor model

Discussions

Question 9

FusionModule1000 is an indoor prefabricated all in-one data center solution.
A. TRUE
B. FALSE

Answer:

B
FusionModule1000A All-in-One Prefabricated Data Center is a green and reliable outdoor data center
solution.

Discussions

Question 10

FusionModule1000A series solution meets the TIER 4 requirements if it adopts 2N power supply and
distribution system.
A. TRUE
B. FALSE

Answer:

B
(FM1000A does not support Tier 4)

Discussions
To page 2